Introduction
The Council of the Village of Merrickville-Wolford has approved a Master Infrastructure Plan (MIP) to be conducted for the municipality.
At the Special Council Meeting on May 11, 2026, Ontario Clean Water Agency (OCWA) provided a presentation to Council regarding the project overview for the MIP. The presentation is accessible for reference here:
Merrickville Master Plan - Project Overview
The report to Council from the Public Works Department outlining the timeline and process of initiating the Master Infrastructure Plan project is accessible for reference here:
Report to Council – April 27, 2026
The development of the MIP was redirected to OCWA, who developed a Request for Services (RFS) for advertising to qualified firms for the development of the Village MIP.
Council awarded the MIP Tender to JL Richards on May 11, 2026.
FAQs
This is Ontario’s standardized planning process for municipal infrastructure. It is required by the Ministry of Environment, Conservation and Parks (MECP) before upgrading major infrastructure.
It answers 2 major questions:
- Do we need to upgrade our infrastructure?
- What is the best solution to meet current and future needs?
It considers:
- Public health and safety
- Environmental impacts
- Regulatory compliance
- Long-term operating costs
Scope of Work
Type of Load | OCWA’s Scope of Work |
|---|---|
Establish a “Design Basis” for infrastructure, including population projections and associated future flows | Meet with JLR on a regular basis to track progress, mitigate project challenges, handle information requests, and to ensure the project stays on schedule, on budget and meets the expectations and requirements of the Village |
Develop models of water and wastewater systems to analyze how future flows will impact infrastructure | Provide technical review of all deliverables throughout the development of the MIP |
Develop alternative solutions and evaluate them to determine the preferred solutions for implementation and development | Manage the financial aspects, scheduling, and overall coordination of meetings and allowing Village staff to invest only a minimal amount of time to drive this project to successful completion |
Follow consultation requirements of the Class EA process | |
Create a 5-year Implementation Plan that provides schedule and budget for projects to be prioritized in the next 5 years |
Next Steps