Week of August 10, reconstruction of areas of Corktown Road will be ongoing and expected to completed. Grading is ongoing to remove potholes and shape the surface.
Week of August 17, grading and surface granular placement.
Minor delays may be expected due to one lane of traffic and grading operations.
We thank you for your patience during the project