Please be advised that road work has begun on Read Street, HF McLean Road, and Collar Hill Road projects.
Below is the estimated timeline for project completion. Please note that the provided timeline is weather permitting and that there may be some slight changes or delays dependent on the weather.
September 25-27th
- Culvert Replacement and Milling to begin on Read Street
September 30 – October 4th
- Grading to start on Read Street. Milling to be started and completed on HF McLean and Collar Hill Roads, and grading to be completed on Read Street.
- HF McLean Road grading
- Paving to be completed on Read Street and Collar Hill Road
October 7-11th
- Paving, ditching and shouldering to be completed on HF McLean Road
Thank you for your cooperation in ensuring that the road construction projects are completed in a timely manner.