The contractor has begun work on Wellington Street (weather and resources pending).
- Completion of the layout and commissioning of the temporary water
- Completion of Asphalt Removal
- Completion of Concrete Curb & Sidewalk Removal
- Installation of Temporary Pedestrian Walkway (Compacted Granulars)
- Potentially Starting the sewer work at St. Lawrence Street heading westerly.
We do not expect and disruptions to the water system during this time.
Garbage/recycling collection will take place as usual. If changes to garbage and recycling collection is expected, residents will be notified.
We thank you in advance for your patience and understanding.