Over the next two weeks, crews will continue making significant progress on underground infrastructure and road reconstruction works.
Planned activities include:
- Sanitary, storm sewer, and watermain installation from St. John Street toward St. Patrick Street
- Road building operations following underground service installation
- Completion of subdrain installation
- Water chlorination and commissioning of new infrastructure
- Service tie-ins to homes and businesses on Wellington Street West
- Sidewalk and curb preparation
- Installation of Enbridge carrier pipe for the gas expansion project
- Completion of various CCTV inspections
- Storm sewer repair at Main Street West and St. John Street
- Closure at the intersection of Wellington and St. Patrick Streets
We appreciate your patience and cooperation as these important improvements continue.