Wellington Street West Construction Update: September 9 to September 23

Over the next two weeks, crews will continue making significant progress on underground infrastructure and road reconstruction works.
Planned activities include:

  • Sanitary, storm sewer, and watermain installation from St. John Street toward St. Patrick Street
  • Road building operations following underground service installation
  • Completion of subdrain installation
  • Water chlorination and commissioning of new infrastructure
  • Service tie-ins to homes and businesses on Wellington Street West
  • Sidewalk and curb preparation
  • Installation of Enbridge carrier pipe for the gas expansion project
  • Completion of various CCTV inspections
  • Storm sewer repair at Main Street West and St. John Street
  • Closure at the intersection of Wellington and St. Patrick Streets

We appreciate your patience and cooperation as these important improvements continue.

Office Hours

Monday - Friday
8:3oam to 4:30pm
Closed daily from 12:00pm to 1:00pm

Office Location

317 Brock Street West,
P.O. Box 340
Merrickville, Ontario, K0G 1N0

logo white

Contact Us

Staff Directory

Phone: 613-269-4791
Fax: 613-269-3095

Office Location

317 Brock Street West,
P.O. Box 340
Merrickville, Ontario, K0G 1N0

Office Hours

Monday - Friday
8:3oam to 4:30pm
Closed daily from 12:00pm to 1:00pm